The Complete Guide to Generator Sizing & Redundancy for Tier III & Tier IV Data Centers

Data Center Operations in Action scaled
Powering Industries for 50+ Years

The Complete Guide to Generator Sizing & Redundancy for Tier III & Tier IV Data Centers

Server Racks and Network Infrastructure

The Unacceptable Cost of Downtime for Data Centers & Information Technology

In the data center world, uptime isn’t just a goal; it’s the entire business model. A single minute of downtime can cost hundreds of thousands, or even millions, of dollars in lost revenue, SLA penalties, and damage to your reputation. While the utility grid is the first line of defense, it is never a matter of if it will fail, but when.

That’s where a meticulously planned backup power system becomes the most critical asset in your facility. This isn’t just about buying a generator; it’s about engineering a resilient, redundant power infrastructure that guarantees continuity.

At Generator Source, we’ve spent decades designing and deploying mission-critical power systems. In our experience, the most successful data centers are those that master two fundamental concepts: precise sizing and intelligent redundancy.

This guide will walk you through the exact methodologies data center operators use to ensure the power is always on. We will cover:

  • Understanding and calculating your facility’s true power load.
  • The essential formulas for generator sizing, including critical derating factors.
  • A clear explanation of redundancy models (N, N+1, 2N) and how they align with Uptime Institute Tiers.
  • The key components that support your generators, from the UPS to the ATS.

Chapter 1: Sizing Your Generator – Beyond the Nameplate

Incorrect generator sizing is one of the most common and costly mistakes we see. Under-sizing leads to system failure during an outage. Over-sizing leads to wasted capital, unnecessary fuel consumption, and potential “wet stacking” in diesel engines.

Accurate sizing starts with understanding your total facility load.

Step 1: Calculate Your Critical IT Load
This is the power consumed by your servers, switches, and storage arrays. It is the entire reason your facility exists.

Step 2: Understand Your PUE (Power Usage Effectiveness)
Your IT equipment is only part of the story. You must also power the extensive cooling and mechanical systems that support it (CRAC units, chillers, pumps). PUE is the ratio of the total power entering your facility to the power used by the IT equipment.

PUE =

IT Equipment Energy
Total Facility Energy​

A typical PUE is around 1.5. This means for every 1MW of IT load, you need 1.5MW of total power to run the facility.

Step 3: Calculate Your Total Power Requirement
With your IT Load and PUE, you can find your total required power.

Example:

  • You have an IT load of 1,000kW.
  • Your facility has a PUE of 1.4.
  • Total Required Power = 1,000kW×1.4=1,400kW.

You need a generator (or generator system) capable of supplying at least 1,400kW of continuous power.

Expert Tip: Don’t Forget Derating and Future Growth
A generator’s nameplate rating is for ideal conditions. In the real world, factors like altitude and high temperatures reduce its actual output. Our experience operating in high-altitude locations like Colorado shows that a generator can lose up to 3% of its power output for every 1,000 feet above sea level.

Rule of Thumb: Always size your generator system with at least a 20-25% buffer above your calculated load to account for derating and future expansion.

For our 1,400kW load, you should be looking for a system with a capacity of at least 1,750kW.


Chapter 2: Redundancy Models – The Heart of Data Center Tiers

Sizing gets you one generator. Redundancy ensures you are never dependent on that single piece of equipment. This is the core principle of the Uptime Institute’s Tier system.

N: The Baseline
‘N’ represents the minimum power capacity needed to support your total load. In our example, N = 1,750kW. A Tier I data center might have an N design. It has no redundancy. If the generator fails during an outage, the data center goes down.

N+1: The Industry Standard for Tier III
An N+1 system provides one additional unit beyond the minimum required (N). For a facility needing 4,000kW (4MW) of power, an N+1 design could be:

  • Three 2,000kW generators.
  • Here, N = two generators (4,000kW). The third generator is the “+1” spare.
  • This allows any single generator to fail or be taken offline for maintenance without impacting the data center’s operations. This is known as “concurrent maintainability” and is a key requirement for Tier III certification.

2N: Maximum Fault Tolerance for Tier IV
The gold standard. A 2N system is two completely independent, mirrored power systems. Each system is capable of supporting the entire data center load on its own.

  • For a 4,000kW load, a 2N system would have two separate plants of 4,000kW each.
  • For example, System A has three 2,000kW generators (N+1) and System B has its own independent three 2,000kW generators (N+1).
  • There is no single point of failure. You can lose an entire power plant and the facility remains online. This is “fault tolerance” and is required for Tier IV certification.

Chapter 3: The Supporting Cast – UPS, ATS, and Switchgear

Your generators are the stars, but they can’t perform without a strong supporting cast.

  • Uninterruptible Power Supply (UPS): When utility power is lost, the UPS batteries provide instantaneous power to the IT load. This critical system bridges the 10-20 second gap it takes for the generators to start up and stabilize.
  • Automatic Transfer Switch (ATS): The ATS is the brain. It senses the loss of utility power, signals the generators to start, and then seamlessly transfers the facility’s load from the utility to the generator system. In a 2N system, highly sophisticated ATS units manage the power flow from both independent systems.
  • Paralleling Switchgear: This is essential for N+1 and 2N systems. It allows multiple generators to synchronize and run together (“in parallel”) to function as a single, large power source. This expert-level equipment is what enables scalability and redundancy.

Backup power for 100% Uptime

Data Center Operations in Action

Designing a backup power system for a Tier III or Tier IV data center is a complex engineering challenge. It requires a deep understanding of electrical loads, a forward-looking approach to growth, and an unwavering commitment to redundancy.

By correctly calculating your load (N), planning for the future, and implementing the right redundancy model (N+1 or 2N), you can build a power infrastructure that makes downtime a non-issue.

Your Next Step
This guide provides the foundational knowledge for your project. The next step is to apply it to your specific facility. Sizing and redundancy calculations involve many variables unique to your site.

Contact the mission-critical power experts at Generator Source for a no-obligation consultation. Our team can help you design a compliant, reliable, and cost-effective system tailored to your exact needs.

Immediate Availability

STAY PREPARED | STAY POWERED

Browse 350+ new, used and surplus industrial generators available now and ready to ship.

1000 4000kW Generators for Sales Generator Source
generator source maintenance person

24/7 Emergency Service

STAY PREPARED | STAY POWERED

From preventive maintenance to full engine rebuilds, our certified technicians have you covered. Our rental generators ensure uninterrupted power during any service or outage.